334b Komokoriki Hill Road, Warkworth
Project type
Building Earth and Timber in Makarau
Date
1 November 2022
Location
Makarau
Building Earth and Timber in Makarau
Overview
On a rain-soaked site in Makarau, north of Auckland, a non-standard home took shape. Its rammed earth walls, macrocarpa timber, corrugated steel roof and off-grid services made it unlike a typical house.
Estimated value: $392,338 including GST (original estimate, June 2022, house and associated services)
As project manager and quality assurance lead, Francois Buys was responsible for keeping the project on track, the costs under control and the work up to standard.
Planning Before the First Trench
The project started with a measured estimate. QS Quote worked through the plans and specifications, measured quantities for each element and priced them at current market rates. That gave the owners a clear budget and gave the team a baseline to manage against.
Planning also covered the items that are easy to overlook on an earth build: testing subsoil before construction, arranging survey and engineering inputs, and confirming which items the owners would supply directly, such as solar, septic and water tanks.
Managing the Build
As project manager, Francois coordinated the builder, the subcontractors and the owners over a sontruction phase of five months.The contract was cost-reimbursement, so the owners paid actual costs plus a margin, under the Construction Contracts Act 2002. That structure only works when someone watches the numbers closely every week.
Quality Assurance Throughout
Earth construction depends on consistent work, so quality checks were built into the process rather than left to the end. Francois's QA role included:
• Material testing: Subsoil mixes sampled and tested, with test cylinders taken to confirm strength.
• Inspections: Checkpoints such as formwork, reinforcement, bond beam, framing and wall lifts, and any council or engineer inspections.
• Defect tracking: Defects were logged, rectified and closed out before handover.
• Finish review: Completed walls, joinery and services checked against the specification.
Owners were told in advance that rammed earth walls change as they cure, with colour and texture settling over months.
Delivery: On Time and On Budget
• Estimated value: $392,338 including GST, original estimate, June 2022.
• Final cost: $441,317- that included $48,979 variation orders and extras.
Lessons from the Build
• Test local materials early. Subsoil mixes need sampling and testing before construction starts.
• Price before you build. A measured estimate gives owners and the team a baseline to manage against.
• Track costs weekly. Cost-reimbursement contracts need regular reconciliation against the estimate.
• Agree owner-supplied items early. Solar, septic and water tanks often sit outside the builder's scope.
• Build quality checks into the programme. Inspections at each stage catch problems while they are still cheap to fix.
A Home Built to Last
The finished home is warm, durable and largely independent of the grid. Delivering it took more than good design. It took steady project management, close cost control and quality checks at every stage.